Warminster Railway Station

Client: Great Western Railway

Project Overview

Warminster Railway Station

55 m²

Service: Roofing

Sector: Rail

  • Approved Contractor: MLG UK Ltd
  • System Installed: Polyroof Protec
  • Client: Great Western Railway
  • Duration: 2 weeks
  • Work Carried Out: Flat roof overlay, liquid waterproofing, working adjacent to asbestos

Scope of Work

A 55 m² flat roof overlay above the café at Warminster Station for Great Western Railway, replacing a failed mineral felt membrane that had trapped water beneath it.

  • Fixed tower scaffold and edge protection erected for safe working at height
  • Holes cut in the existing membrane to drain trapped water, then a wet vacuum system used to remove the excess
  • Polyroof DP primer applied to the existing mineral felt membrane
  • New Polyroof drip trims installed for correct detailing
  • Polyroof Protec waterproofing applied across the full 55 m²

Systems installed

  • Waterproofing: Protec waterproofing system across 55 m² (Polyroof)
  • Primer: DP primer to the existing mineral felt membrane (Polyroof)
  • Trims: New drip trims for correct detailing (Polyroof)

Challenges & Constraints

01
Water in the build-up

The failed mineral felt membrane had trapped water beneath it, and an overlay applied onto a wet deck fails.

02
Asbestos next door

An adjoining asbestos roof sat alongside the work area, with a hard rule that no works would be undertaken on it or directly adjacent to it.

03
Deck condition unknown

Whether the deck beneath the felt was sound enough to overlay could not be assumed before the trapped water was removed.

Project Execution & Techniques

Drained and vacuumed

Holes were cut in the existing membrane to drain the trapped water, then a wet vacuum system was used to remove the excess before anything was applied.

Primed and trimmed

Polyroof DP primer was applied to the existing mineral felt membrane and new Polyroof drip trims were installed for correct detailing.

Protec across 55 m²

Polyroof Protec waterproofing was applied across the full 55 m² of the café roof.

Access built first

A fixed tower scaffold and edge protection were erected for safe working at height above the station café.

Outcome & Long-Term Benefits

A drained deck first

The trapped water was drained and extracted before the overlay went on, so the new system was applied to a dry deck rather than over a wet one.

Priced with a caveat

The works were priced with a clear caveat that further uplift would be required if the deck proved porous or unsuitable for overlay, rather than quoting a figure that could not hold.

One manufacturer throughout

Primer, drip trims and waterproofing were all Polyroof, installed by a Polyroof approved installer, so the roof is a single system rather than an assembly of equivalents.

Asbestos left untouched

The adjoining asbestos roof was treated as a hard boundary, not a judgement call on the day, and nothing was carried out on or directly adjacent to it.

Conclusion

The café roof at Warminster Station was 55 m² of failed mineral felt with water trapped in the build-up, next to an adjoining asbestos roof. Both facts shaped the job: an overlay onto a wet deck does not last, and the asbestos boundary was a line the works would not cross.

MLG cut and drained the trapped water, wet-vacuumed out the excess, primed the existing membrane with Polyroof DP, fitted new drip trims and applied Polyroof Protec across the full area, working from a fixed tower scaffold with edge protection. The £24,982 quote carried an honest caveat that uplift would be needed if the deck proved porous, the alternative being a lower number that would not have survived contact with the roof.